HZS concrete mixing plant daily maintenance work are:

1, to ensure that the machine and the surrounding environment clean.

2, in time to clear the accumulation of material within the hopper, so that the sensor back to normal.

3, check the lubrication point of the oil is sufficient, the gas system in the oil mist should keep enough oil.

4, check the motor, electrical overheating, abnormal noise, whether the instrument is normal, the signal system is intact.

5, often check, adjust the cylinder, butterfly valve and solenoid valve, so that open and close meet the requirements.

6, often check the system, if leakage of dust, leakage, oil leakage and leakage phenomena such as timely treatment.

7, mixer and hopper should be cleaned once every four hours, so as to avoid residual concrete consolidation, hinder the normal operation.

8, each class should be free air compressor, gas tank and filter and other internal water, and remove the operation of the failure.

9, butterfly valves, mixers, electromagnetic valves, air filters and oil mist, etc. in accordance with the instructions for maintenance.