Treatment of concrete mixing plant after completion

2017-10-09

1. After the completion of the work should be put off the pump, additive pump, water tank, additive tank, water, additives pipeline in the residual water, additives to prevent damage to the pump and its pipeline, and start the pump pump 1-2 minutes.
 
2. Clean the inside and outside of the mixing tank wall, the discharge port, the mixing shaft and the concrete residue on the discharge door. Wash these central flushes with water. If necessary, add a small amount of stone and water to stir for a few minutes. Water washing car, additive tank and its supply system.
 
3. The smooth points are located in the mixer shaft, the storage hopper and weighing bucket door, tape transport, machine wheel, pressure roller, roller, bearings, transmission chain, screw shaft, the lower end of the bearing and the host gear.
 
4. Check the wear of the blade, scraper, agitator, etc. If necessary, adjust the gap or change; Vibrator coupling bolt with or without loosening; Check the electrical contactor; Intermediate relay static contact can damage and burn The
 
Above is the concrete mixing plant consumption work to stop after the end of the inspection and maintenance matters, although more complicated, but must do these basic work to ensure the smoothness of consumption.